Problem guide
Purchase approvals leave the work waiting
People wait on purchases because approval is only the first of two steps, and both happen somewhere the person who needs the item cannot see. In ServiceTitan, a purchase order above the user's tier sits as Pending on the Requests tab until an approver acts, and it gets a PO number only then. Someone in the office still has to send it to the vendor. Put the request where the approver already looks, name a backup, and name who sends.

How it actually happens
The tech opens the unit at ten in the morning and finds the part that failed. It costs more than he is allowed to buy. From that moment the job depends on two people who are not on the roof: the person who can approve the purchase and the person who sends it.
The same moment happens off the roof. A kitchen manager's walk-in cooler fails at four in the afternoon. A property's maintenance supervisor has a quote for a water heater that is over the owner's limit. A department's staff member needs a part that only purchasing can order. Each one has a need, a price and a person who is not in the room.
In ServiceTitan the path is documented step by step. With approval tiers turned on, a request above the tech's tier becomes a Submit for Approval. It sits as Pending on the Requests tab until an authorized approver acts, and only then does the system generate a PO number. If approver email notifications were never switched on, the approver finds out when he happens to open that tab, or when the lead calls him. A tech working from the mobile app can create the PO from the job, and the office gets a notification to review and send it. Either way, someone at a desk finishes the order.
Housecall Pro builds the same handoff into the button. A field tech can draft a purchase order on mobile, but the button reads Send to Admin, and the order is finished and sent on the web. Simpro, with Restrict Unapproved Orders turned on, will not email an order to the supplier until someone with the right security group moves its Stage from Pending to Approved. Acumatica puts an approved order into Pending Printing or Pending Email before it is open. Across these products the pattern repeats: approval and sending are two separate events.
That is why the wait is longer than anyone thinks. The manager remembers approving it in two minutes, once he saw it. He does not count the hour before he saw it, or the forty minutes after, when the approved order sat in the office until the coordinator got off a call. The person who needs the item counts all of it. The person who opened a 2025 thread on r/procurement described the approver side plainly: sometimes people do not reply for days, or ask the same questions over and over.
Construction adds another approval on top. Under the unmodified A201-2017 the contractor performs no work that needs a submittal until the architect approves it, and the architect acts on the submittal schedule or with reasonable promptness. A contractor that holds its internal purchase order until that approval returns runs the review and the buy one after the other. Then, on Procore and Vista, the PO reaches accounting only once its status is Approved, on an hourly sync.
Refrigerant has a gate of its own. The supply house can sell it only to a certified technician, or to an employer that proves it employs one. An approval in the office does not change that at the counter.
What the wait costs
Nobody publishes this number. No trade association or agency in this research measures time lost to internal purchase approvals. You can still price an hour of it: the national median wage for an electrician in May 2025 was $30.38, before burden and the truck. Jamie Sullivan of Staff Electric in Milwaukee told EC&M in 2023 his electricians probably spend only 40 to 45 percent of their time installing. Your own request, approve, send and receive times will tell you how much of the rest is this wait, whatever your people are paid.
Signs you have this problem
- Someone texts a manager for a PO number and the work stops until he answers
- Approved purchase orders sit in the office for hours before anyone sends them to the vendor
- People put purchases on a personal card and turn in the receipt at the end of the week
- The approver says the request never reached him, and nobody can show where it went
- Work is rescheduled for an item that was available the whole time
What usually causes it
- Requests over a person's limit go to one approver with no reminder, no backup and no clockApproval drag
- Approval and sending are separate steps owned by different people, and the gap between them belongs to nobodyThe handoff gap
- Pending requests sit in a Requests tab, an inbox or a text thread that only the approver opensThe invisible queue
- The request comes from where the work is and the decision is made in the office, with no shared view of the job, the price or the stockThe field-to-office split
Find your cause
Ask these in order. The first yes is usually where yours starts.
- Do approved purchase orders wait in the office before they are sent to the vendor?If yes: the gap is the send step, not the approval. Name who sends and set a time for it.
- Does every request over a person's limit go to one approver, with no backup?If yes: the wait is that person's calendar. Add a backup approver and a reminder.
- Do approvers call the requester back before they decide?If yes: the request is missing the job, the price or the cost of waiting. Make the request carry the decision.
- Do people buy on personal cards to avoid asking?If yes: the limits are lower than the work needs, or nobody trusts the process to answer in time. Check the tier table against the last month's purchases.
- Do items arrive before the order is approved, or get received outside the system?If yes: approval runs behind the purchase. Look at your receiving step, since Simpro mobile and similar tools cannot receive against an unapproved order.
How it breaks in each industry
- HVAC and refrigeration service
- The failed part is found with the customer standing there, and the lead's tier is often lower than the price of a compressor or a coil. Refrigerant adds a second gate at the counter: the wholesaler can only sell it to a certified technician or to an employer with written evidence that it employs one, so an approval in the office does not release the cylinder by itself.
- Electrical contractors
- Small material runs wait on the same approval chain as switchgear. On long-lead equipment the approval delay stacks on top of the manufacturer's lead time, which AGC members already name as a source of project delays, so a day lost before the order is placed is a day added to the energize date.
- Commercial mechanical and construction trades
- The purchase waits on two approvals: the internal buy and the architect's submittal review. Under the unmodified A201-2017, the contractor performs no work that requires a submittal until it is approved, and the architect acts within the submittal schedule or with reasonable promptness. If the internal PO waits until the submittal comes back, the two waits run end to end instead of side by side.
- Property management
- Repairs above the limit in the management agreement need the owner's approval. The maintenance supervisor has the vendor's quote, the property manager emails the owner, and the tenant waits on a repair nobody can authorize until the owner reads the email.
- Restaurants and hospitality
- A walk-in cooler or a dish machine fails during service. The general manager can approve a small repair, but anything larger goes to an owner or a district manager, and the repair company will not dispatch the part without a PO number. Product sits on ice while the request waits.
- Local government and community organizations
- Purchases move through a requisition that a department head approves and purchasing turns into a purchase order. Each step is a separate queue, and the crew or staff member who asked for the item cannot see which queue it is in.
Where it breaks between systems
- ServiceTitan purchase approval tiers
- With PO Approval Tiers on, a user whose order exceeds the assigned tier clicks Submit for Approval instead of creating the PO. The request stays Pending on the Requests tab until an authorized approver approves or rejects it, and the PO number is generated only after approval.[1]
- ServiceTitan mobile to the office
- A tech with the Create purchase order permission can create a PO from the job, and the office receives a notification to review and send it. The other path, Invoice then Request Items, makes a requisition that the office converts into a PO. Sending is its own step, by PDF, XLS, or electronically only for vendors on the Full Procurement Integration.[1]
- ServiceTitan approval setup
- Approver email notifications are a setting you choose, tiers are assigned to roles, and each tier can count the PO total with taxes and shipping or the subtotal without them. A rejected request shows who rejected it, when and why, and can be resubmitted.[2]
- ServiceTitan and QuickBooks Online
- A purchase order exports to QuickBooks Online as a single item called Service Titan PO Item carrying the whole cost, not the materials as entered, and classes are not tied to the business unit, so they are added to each PO by hand after export.[4]
- Housecall Pro purchase orders
- A field tech with the right permission can build a PO draft on mobile, but the Send button becomes Send to Admin, which emails the admins. The mobile app cannot complete or send the order; that happens on the web. The feature is limited to the HVAC, Electrical and Plumbing packages.[5]
- Simpro purchase orders
- With Restrict Unapproved Orders turned on, a PO must be approved before it is emailed to the supplier. Employees can be allowed to approve up to a set value, and anything above goes to someone with full approval permissions, who moves the Stage from Pending to Approved.[6]
- Simpro mobile receiving
- On mobile, Receive Goods is offered only when the purchase order has been approved in Simpro, so parts that arrive against an order still waiting on approval cannot be received in the app.[7]
- FieldEdge and QuickBooks
- A parts request can be saved for later, and each click of Create PO with Selected Parts generates a new purchase order in QuickBooks. The Purchase Order number is maintained in QuickBooks and cannot be edited in FieldEdge.[8]
- Acumatica purchase orders
- When approval rules apply, clearing Hold moves a PO to Pending Approval, where it stays until every required approval is done. After the last approval it becomes Pending Printing, Pending Email or Open, so an approved order can still be waiting on a print or email step.[9]
- Procore and Trimble Vista
- A Procore purchase order exports to Vista only with its status set to Approved, a contract company linked to a synced Vista vendor, an ID of 30 characters or less, a title of 60 or less, and at least one line on a Vista cost code. The automatic sync runs once an hour and the schedule cannot be changed.[10]
- Trimble Vista approval limits
- With Approval limit is based off of document total checked, the limit applies to the whole PO; unchecked, it applies by item type: job, inventory, expense or equipment. An approver's workflow approval limit overrides that person's spending limit.[11]
- ServiceM8 and Jobber
- ServiceM8's help center says it has no built-in way to create and send purchase orders and points to its Add-on Store. In Jobber's community, a user asking how to email a vendor a PO and keep it open until the goods arrive got a staff answer marked as the solution: use a custom field for the PO number.[12]
By the numbers
| Figure | What it measures |
|---|---|
| 35%[17] | Firms with a delayed project that named longer lead times for materials as a cause, out of nearly 1,400 firms in the AGC and NCCER 2025 Workforce Survey (August 2025); 78% reported at least one delayed project. Lead time, not approval time. |
| 41% and 28%[18] | Firms citing long lead times for electrical equipment such as transformers and switchgear (41%) and for mechanical equipment such as HVAC gear (28%) as a source of project delays, AGC 2024 Workforce Survey. |
| $30.38 an hour[19] | National median wage for electricians, May 2025 (BLS Occupational Employment and Wage Statistics, released May 15, 2026). Wage only, before burden, so it is the floor for what an electrician standing at the counter costs. |
| $29.33 an hour[20] | National median wage for heating, air conditioning and refrigeration mechanics and installers, May 2025, same BLS release. No survey in this research measures purchase approval time itself; these wage rows price the hour, and the measurement below counts the hours. |
| 35 to 45 percent[21] | CII's statement that direct work typically amounts to no more than 35 to 45 percent of a craft worker's time on the job (Craft Productivity Enhancements Workshop, October 2008, abstract of a members-only presentation). It covers all non-direct time, not waiting on approvals alone. |
Rules that apply
- 40 CFR 82.154(c)(1)(i) and (ii), refrigerant sales restriction[14]
- No one may sell class I or class II refrigerant, or a non-exempt substitute, for use as a refrigerant unless the buyer is a certified technician under 82.161 or employs at least one and gives the seller proof. An approved PO does not get a cylinder across the counter if the person picking it up is not covered.
- EPA Section 608 refrigerant sales restriction guidance[15]
- The restriction covers refrigerant in cylinders, cans and drums, with an exception for small cans of substitute refrigerant for car air conditioning. An employer can buy if it gives the wholesaler written evidence that it employs a certified technician, so keep that evidence on file at every supply house the crews use.
- AIA A201-2017, 3.12.5 and 3.12.7, submittals[16]
- Under the unmodified A201-2017, the contractor submits on the approved submittal schedule or with reasonable promptness so as to cause no delay, and performs no work that requires a submittal until the architect approves it. The form bars performing the work, not placing the order; ordering early is a business risk the contractor chooses.
- AIA A201-2017, 4.2.7, architect's review[16]
- The architect acts on submittals per the approved schedule or, without one, with reasonable promptness. A201 sets no day count; a fixed review period, when there is one, lives in the supplementary conditions or Division 01.
Measure it in your own shop
From: Purchase requests and purchase orders in your operating or ERP system: the Requests and Pending tabs in ServiceTitan, which show who approved a request and when; the Stage column in Simpro; commitments in Procore; requisitions in your accounting system; or the text and email threads where approvals actually happen.
- Pick every purchase order from the last month that needed someone else's approval.
- For each, record four times: requested, approved, sent to the vendor, and received. Where your system does not store a sent time, use the time the PO left its pending list or the vendor's order confirmation.
- Subtract each time from the next, and note whether anyone was waiting on the item during any of the gaps.
- Count the jobs, appointments or services that were rescheduled or needed a return trip because a purchase was still pending.
Reading it: The median of each gap tells you which step to fix first. The count of rescheduled work, times your burdened hourly cost and trip cost, is what the wait costs you, a number no published survey gives you.
What does not fix it
- Raising everyone's limit
- It removes the wait and the control together, and it does nothing for the send step. The orders still sit until someone in the office pushes them to the vendor.
- An approvals group text
- Requests scroll out of sight, nobody knows who answered, and the decision never reaches the purchase order or the job. It moves the queue from one phone to several.
- A purchasing module with approval tiers
- ServiceTitan, Simpro, Vista and Acumatica all have tiers already. Tiers decide who must approve. They do not make that person answer, and in most of these systems an approved order still waits on a separate send.
What to try this week
- Publish the dollar lines by roleWrite one table: what each role can buy without asking, and whether the limit counts tax and freight. ServiceTitan lets you set tiers on the PO total or the subtotal; pick one on purpose, then put the table where people make purchases, whether that is a truck, a kitchen office or a nurse's station.
- Give every approver a backup and a reminderTurn on approver email notifications where your system offers them, and name a second approver for each role. If a request has not moved in thirty minutes during work hours, the backup decides.
- Name who sends, and how fastAn approved order is not an order until the vendor has it. Pick the person who sends approved POs, and set a time, such as within fifteen minutes of approval during business hours.
- Make the request carry the decisionRequire the job or cost center, the item, the price, the vendor and what happens if the answer is no. An approver who can see the cost of waiting decides faster than one who has to call back.
- Time ten real requests from your own recordsPull the last ten purchase orders that needed approval and write down when each was requested, approved, sent and received. The longest of those three gaps is where to start.
Put a number on it
- Approval wait calculator: Calculate the paid crew hours and dollars lost each year while crews wait for purchase, change order and schedule approvals.
Where do-it-yourself stops
These steps shorten the wait and make it visible. They do not put the request in front of whoever can answer it, escalate it on a clock, send the approved order the moment it clears, or show the requester where it stands. That takes a tool built around your approval tiers, your operating system and your vendors. That is what a Workflow Spec designs.
Questions people ask
Is there a benchmark for how long a purchase approval should take?
No. No trade association or government survey in this research measures internal purchase approval time. Time your own last month of requests from approval to send to receipt; that is the only number that will hold up.
Does an approved purchase order in ServiceTitan go to the vendor on its own?
No. After approval, ServiceTitan generates the PO number and moves it to the Pending tab as an active purchase order. Sending is a separate step, by PDF or XLS, or electronically for vendors set up with the Full Procurement Integration.
Should the approval limit include tax and shipping?
ServiceTitan lets you set tiers on the PO total, which includes taxes and shipping, or the subtotal, which excludes them. Decide once and print it with the limits; someone who guesses wrong sends a request that did not need to wait.
Can our tech buy refrigerant with an approved PO if he is not certified?
Not under 40 CFR 82.154(c). The seller needs a certified buyer, or an employer that employs a certified technician and provides proof. EPA's guidance calls it written evidence, so the company can file it with the supply house once.
Can we order equipment before the submittal comes back approved?
The unmodified A201-2017, at 3.12.7, bars performing work that requires a submittal until the architect approves it. It does not mention ordering. Releasing the order early is a risk you weigh against the lead time, job by job.
Next step